TL;DR. PMMI’s 2025 outlook projects continued end-of-line automation investment in 2026, with lead times on robotic cells still 24–30 weeks. For buyers: issue RFQ now if you want installation by Q3 2026, and budget 15–20% for integration contingency. This article breaks down PMMI’s findings and what they mean for your 2026 capital plan.
By Ryan Huang, Sales Application Engineer. Ryan has tracked PMMI’s annual outlook for 6 years and advises plants on capital timing.
1. PMMI’s 2025 findings
PMMI’s 2025 business outlook survey found that 62% of CPG plants plan to increase end-of-line automation spend in 2026, up from 54% in 2024. The drivers are labour cost, e-commerce SKU growth, and the need for OEE improvement.
Statista’s packaging equipment data corroborates: lead times on robotic palletizing cells have stayed at 24–30 weeks since mid-2024, with no sign of easing in 2026.
2. Expected 2026 lead times
| Equipment | Lead time |
|---|---|
| Semi-automatic case sealer/erector | 8–12 weeks |
| Automatic case sealer/erector | 12–16 weeks |
| Stretch wrapper (turntable) | 10–14 weeks |
| Robotic palletizer/case packer | 24–30 weeks |
| Integrated end-of-line line | 36–52 weeks |
3. What this means for your 2026 capital plan
- Issue RFQ for robotic cells by December 2025 for Q3 2026 installation.
- Budget 15–20% contingency for integration surprises.
- Lock in pricing early — steel and servo prices are rising 5–8% annually.
- Book a factory acceptance test (FAT) before shipping.
- If you need a cell before Q3, consider a semi-automatic or refurbished unit as a bridge.