TL;DR. Most end-of-line equipment problems are not hidden inside the machine; they show up at commissioning, when the cell is first run together and the FAT and SAT checks are either done properly or skipped. A machine that passes a supplier’s bench demo can still arrive with misaligned feeds, weak guarding, undocumented change parts, or a cycle rate that only holds on a clean sample pack. The acceptance phase is where the buyer confirms that the erecting, sealing, strapping, wrapping and palletizing stations meet the written specification, run together at the planned rate, and leave behind the documentation and spares the plant will need. This note walks through what FAT and SAT each cover, what to verify before the factory visit, the station-by-station checks we run on an end-of-line cell, how ramp-up and sign-off should work, the failures we catch most often at commissioning, and what these checks mean for your buying decision in 2026. Figures and criteria are planning references; your acceptance basis should follow the written specification and the standards that apply to your market.
By Sarah Liu, Packaging Equipment Engineer — Bundling and Secondary Packaging. Sarah has spent 12 years specifying, commissioning and troubleshooting banding, strapping and shrink-bundling stations across CPG, print, publishing and paper-goods plants. She has audited collation feeds and band-closure heads on more than 180 secondary-packaging cells, and works mostly from the floor: watching bundles discharge, checking band position and joint appearance, and counting reworks before signing off a line.
Why commissioning decides whether the cell performs
An end-of-line cell is a chain of stations: cases erected, filled or packed, sealed, strapped or bundled, wrapped, then palletized. Each station may be sound on its own, but the cell only performs when the feeds, timing, guards and discharge between them line up. Commissioning is the phase where that chain is tested as a whole. Before it, the equipment has been built and maybe run on the supplier’s floor; after it, the line is handed over for production and the acceptance criteria are harder to revisit.
We see two patterns after install. In the first, the buyer accepted the machine on a short demo and found out during ramp-up that the feed could not keep up, the changeover took far longer than quoted, or the guarding blocked access the operators needed. In the second, the buyer ran a structured FAT at the supplier and a SAT on site, caught the alignment and documentation issues early, and closed them while the supplier was still accountable. The difference is almost always the acceptance process, not the machine brand.
Commissioning also covers the interface to the rest of the plant: utilities, controls, upstream and downstream conveyors, and any data exchange with WMS or MES. Those interfaces are part of the end-of-line integration picture covered in the end-of-line integration guide. A cell that was commissioned in isolation often needs a second round of adjustments once it meets the real line.
FAT versus SAT: what each covers
Factory Acceptance Testing (FAT) happens at the supplier’s or integrator’s site, before the machine ships. Site Acceptance Testing (SAT) happens after install at the buyer’s plant. They answer different questions: the FAT checks that the built machine matches the specification before it travels, and the SAT checks that the installed cell runs correctly in its real location with real product, utilities and operators. The table below compares the two on timing, setting, focus and the main output.
| Step | When it runs | Setting | Main focus | Output |
|---|---|---|---|---|
| FAT | Before shipment, at supplier/integrator site | Supplier’s utilities, sample product or buyer’s samples | Build match to spec, function, controls, guarding, documentation | Resolution list, witnessed test report, release to ship |
| SAT | After install, at buyer’s plant | Real line, real product, real operators and utilities | Installation alignment, interface, production trial, ramp-up handover | Acceptance sign-off, open-issue list, training and spares handover |
The FAT is cheaper to fix at the supplier than after shipping. Alignment, missing parts, control behavior and guarding issues caught at FAT stay in the supplier’s workshop; the same issues caught on site mean a service visit, delayed ramp-up and often a commercial argument over who pays. The SAT is where the plant proves the cell works under production conditions, because nothing about a supplier’s demo room matches a multi-shift floor with mixed SKUs, dust, moisture and operator habits.
What to verify before the FAT visit
A useful FAT starts before anyone travels. The specification, drawings and functional requirements should be fixed in writing, so the test has a basis to measure against. Bring the product samples the machine will actually run, including the worst-condition SKU: the tallest case, the heaviest pack, the most flexible bag, the dirtiest or coldest product. A demo on an easy, clean pack hides the problems that show on your line.
Check that the supplier has the utilities and conditions the machine needs: power, compressed air, vacuum if used, exhaust and drainage. Confirm the documentation package is in preparation: operation and maintenance manuals, wear-parts list with part numbers, electrical and pneumatic drawings, recipes, safety documentation and the spare-parts schedule. Agree the test cases and pass criteria in advance: target rate, acceptable defect level, changeover time, guard interlock behavior, and what counts as an open issue versus a release condition. The structural and utility checks that feed into this are covered in the compressed air and power utility guide.
Station-by-station FAT checklist
On an end-of-line cell, each station has its own acceptance points. Running through them station by station keeps the FAT focused and makes sure a passing arm does not mask a weak feed or seal.
Case erector and feeder
Check that cases open square and feed at the planned rate, that the bottom seal closes cleanly for the board grade in use, and that mis-erected or double cases are rejected rather than jammed downstream. Verify the magazine capacity, the change parts for each case size, and the adjustment between formats. Watch for cases that sit crooked on the conveyor or flaps that do not fold fully, because those faults carry straight into the sealer and packer.
Case sealer and packer
On the sealer, confirm the tape or adhesive seal is consistent across the case range: no skewed tape, gaping flaps or weak joints, and the head pressure and position set for the actual board. On the packer, check placement depth, orientation and count, and that packs land in the required pattern without crushing or scuffing. Run the mixed formats the plant expects, not only the largest or easiest case. The tape-head and seal-process points are detailed in the case sealer tape head guide and the carton sealing defects guide.
Strapping and banding station
Check strap tension and seal joint appearance on the heaviest load, that the strap position lands on the case or bundle, and that the arch and feed clear the pack size range. Verify seal-head wear parts are listed, and the machine rejects a mis-fed strap rather than cycling through a jam. For banding, confirm the band width and material suit the bundle and that joints hold through handling.
Stretch wrapper or shrink bundler
On the wrapper, run the tallest and widest load, check film overlap and hold, and confirm the carriage tension and pre-stretch hold the load without loose film or over-tension crush. On a shrink bundler, verify tunnel dwell, heat setting and film contraction on the actual packs, and that bundles discharge square without wrinkling or tearing. The ancillary top sheet, corner board and carriage choices are covered in the top sheet and corner board guide.
Palletizer or load handling station
Check the build pattern, layer count and pallet change, that the pick or gripper handles every product form in the range, and that the cell clears the pallet, slip sheet and discharge conveyor. Verify guarding zones, access interlocks and the speed at which the cell can safely operate. Confirm the programming or recipe recalls the pattern for each SKU, and review how mixed or irregular cases are handled.
SAT, ramp-up and handover
After install, the SAT re-runs the core checks under production conditions. The machine should be leveled and aligned to the surrounding conveyor, utilities connected and checked for pressure and leakage, and guards and interlocks verified on site. Then run a production trial: real product, real operators, a steady run across the main SKUs, counting finished cases, defects, jams and changeover time. The line balance between stations should be observed through a shift, not assumed from the rated peak. The throughput and line-balance measures are laid out in the line balancing and throughput guide.
Ramp-up is the period after acceptance when operators learn the machine and the team fixes the residual issues. Training should cover daily setup, changeover, routine wear checks, jam clearing and basic fault finding, and the operators should perform these tasks during handover rather than watch the supplier do them. The open-issue list should name each remaining point, who owns it, and the deadline. Preventive routines and spare-parts stocking are reviewed in the spare parts management guide and the preventive maintenance guide.
Documentation and acceptance sign-off
The acceptance package is what the plant keeps after the supplier leaves. It should include operation and maintenance manuals, electrical and pneumatic schematics, the wear-parts and spare-parts list with part numbers and lead times, stored recipes and parameters, safety documentation and guarding records, and the training record for the operating staff. Rank Math aside, the machine’s own documentation matters for EEAT and service continuity: a line without a parts list becomes an orphan once the supplier rationalizes the model.
Sign-off should be tied to the agreed pass criteria, not to the supplier’s schedule. A minor documentation gap can remain as a tracked open issue; a functional defect that affects output, safety or product quality should be resolved before acceptance. Keep the FAT and SAT reports, the defect log and the issue list on file, because they are the baseline for later warranty claims, spare-parts review and any retrofit decisions. The retrofit audit practice that builds on this baseline is in the end-of-line retrofit audits guide.
What This Means for Your Buying Decision
For buyers comparing end-of-line equipment in 2026, the commissioning process is a buying signal as much as the machine specs. A supplier who can define a clear FAT, bring your samples into the test, itemize wear parts and documentation, and stand behind a SAT on site is likely to be easier to support after install. A supplier who resists witnessed testing, leaves change parts or manuals vague, or pushes acceptance on a short demo carries that risk into your ramp-up.
The practical decisions this points to are straightforward. First, write the acceptance criteria into the purchase order rather than negotiating them after build. Include the target rate, acceptable defect level, changeover expectation, documentation list and training scope. Second, require a FAT on your own worst-case samples before shipment, and reserve the SAT for the production floor. Third, price the spare parts and wear schedule alongside the machine, so the five-year view does not start after install with missing part numbers. Fourth, match the commissioning plan to your operator shift and SKU mix; a cell commissioned on a single easy format will not reveal mixed-SKU or changeover problems.
Where you are buying a whole integrated cell, one party should own the FAT and SAT across all stations. Where you are assembling stations from separate suppliers, define who tests each interface, because a feed from one vendor and a packer from another often meet for the first time on your floor. The safety documentation and guarding scope should follow the machinery standards for your market; the relevant control-system safety practice is summarized in the packaging machine safety and guarding guide.
Common commissioning failures and how to catch them
The defects we see most often at commissioning fall into a short list, and each has a check that catches it before acceptance.
| Failure | Where it appears | Catch it by |
|---|---|---|
| Feed cannot keep up at planned rate | Erector, packer or collation inlet | Running a sustained production-like trial, not a short demo; count cases per hour through a shift |
| Changeover takes far longer than quoted | Between SKUs at FAT or SAT | Timing a full format change on a second SKU; reviewing change parts and recipe recall |
| Missing or vague wear-parts list | Documentation handover | Checking part numbers, lead times and spare-stock recommendation before sign-off |
| Guarding blocks required access or interlocks bypassed | Station layout and safety check | Walking operator tasks against guards; verifying interlocks stop the station when opened |
| Seal, wrap or grip works only on clean samples | Worst-condition SKU trial | Testing dusty, cold, flexible or heavy product from your actual line |
| Utility pressure or supply undersized | Connected SAT run | Measuring air and power at the station during cycle; checking for drops under load |
| Stations do not match at the interface | Between vendor-supplied machines | Defining interface responsibility before order; testing the handoff in the SAT |
A second set of issues is documentation rather than function: manuals that describe a different machine, parameters not stored in recipes, or training that leaves operators dependent on the supplier. These surface when you ask the operating staff to run the change and the wear check themselves during handover. If they cannot, the training and documentation are not finished.
Questions to put before acceptance
- What is the written acceptance basis: target rate, acceptable defect level, changeover time and test cases?
- Will the FAT run on our own samples, including the worst-condition SKU, and can our team witness it?
- Which stations does the supplier own at the interface, and how are cross-vendor handoffs tested in the SAT?
- What wear parts and spares are listed, with part numbers, expected life and lead times?
- What documentation is handed over: manuals, schematics, recipes, safety records and training sign-off?
- How is operator changeover, jam clearing and routine maintenance trained and verified?
- What open issues can remain after acceptance, who owns each, and what is the deadline?
- What are the warranty terms, response commitment and parts continuity window after install?
Scenario notes for 2026
A high-volume regular-product line should expect a focused FAT on its main and edge formats, a sustained SAT trial, and a spare-parts stocking list tied to the wear schedule. A mixed-SKU co-pack plant should make changeover time and recipe recall a stated acceptance criterion, because format changes will define its real output. A food or cold plant should verify washdown materials, drainage and product-contact condition during the FAT, not after install. A retrofit into an existing line should confirm the new station aligns to the old conveyor and utilities before the SAT is judged complete.
If you are preparing a purchase or acceptance package, bring the specification, product samples, target rate and SKU range, and the commissioning questions above can be turned into a test checklist for the supplier. The broader line integration and layout decisions sit behind this process in the integration guide, and the standard and compliance side in the GMP and CE compliance guide.
What the standards expect from the safety and acceptance record
For equipment sold into regulated markets, acceptance is not just an internal efficiency check; it is part of the compliance record. Guarding, interlocks, emergency stops and control-system safety performance should be verified against the machinery standards that apply to the destination market, and the record should show what was checked rather than assuming a compliant machine arrived that way. The control-circuit categories and safety functions behind that check are described in the ISO 13849-1 framework, summarized in the packaging machine safety standards guide.
Food, cosmetic and pharmaceutical plants add product-contact and hygiene expectations: materials that resist cleaning, surfaces that drain without trapping residue, and a design that survives washdown without harboring contamination. Those points are easiest to verify at the FAT, where the supplier can open guards and show construction, rather than after the machine is installed around the rest of the line. The food-grade and CE compliance considerations are laid out in the GMP and CE compliance guide. Keep the safety inspection results and any risk-assessment notes with the acceptance package, so a later audit or inspection can trace what was checked and when.
Where the cell exchanges data with an upstream or downstream system, the acceptance check should also confirm the signal exchange: case count, reject status, alarms and any recipe or product-code transfer. A controls issue that only appears when the machine talks to the WMS or MES will not show on a standalone bench run, so the interface test belongs in the SAT rather than a later engineering visit. The connection architecture for end-of-line machines is reviewed in the connected machines and OPC UA guide.
The cost of skipping structured commissioning
Buyers sometimes compress acceptance to save time, or accept on the supplier’s demonstration because the machine looked right on the floor. The savings are small and the costs usually land later. A missed feed or seal problem means lost production during ramp-up, reworked or rejected product, and operator workarounds that become permanent habits. A missing parts list means waiting on lead times for wear items that should have been stocked, and a guarding gap discovered after install is a safety exposure that costs more to fix on site than in the workshop.
There is also a repeatability cost. A cell that was never run through a sustained trial has no baseline for what normal output and defect rate look like. When a later problem appears, the team cannot tell whether the machine drifted, the product changed, or the setup was off. The defect log and acceptance baseline from commissioning are what make that later diagnosis possible. The retrofit audits that rely on this kind of floor record are covered in the retrofit audits guide.
Structured commissioning is not a delay tactic; it is the point where specification, build and production are matched. A supplier who respects that process usually communicates the test plan in advance, invites the buyer to witness, and tracks open issues to closure. The acceptance period should be scheduled into the project timeline rather than treated as a final hurdle after the machine is already on the floor.
Checking supplier references before the order
Before committing, ask the supplier for a reference installation that runs a similar product and line speed, and check what the commissioning and support experience was like. Useful reference questions: did the FAT cover your type of product, how long did changeover take in production, what wear items failed early, how responsive was support after install, and were the manuals and parts list usable on the floor. A reference that matches your SKU mix and volume tells you more than a high-profile showcase on an easy product. The supplier engineering-capacity and continuity checks are expanded in the manufacturer engineering capacity guide and the supplier continuity guide.
How a commissioning sequence typically runs
A practical commissioning sequence moves from build verification to function, then to production trial and handover, and keeping that order prevents a later step from masking an earlier fault. The first pass confirms the machine is built to the drawings: guards fitted, fittings tight, cables routed, controls powered, and the correct wear parts installed. The second pass checks function station by station: feeds, motions, rejects, alarms and interlocks each operate as specified, before the line is run at speed. The third pass runs product through the cell at the planned rate, observing defects, jams and changeover under production-like conditions. The final pass hands the machine to the operators, confirms training and documentation, and closes the open-issue list.
On a multi-station cell, commissioning should follow the material flow: the upstream feeder and erector are settled before the sealer and packer, then the wrapper and palletizer. Running the whole cell at speed before the feed is steady mostly produces jams that look like a downstream fault but start upstream. When a defect appears, trace it back to the first station where the pack or case went wrong, rather than adjusting the station where it was noticed. This is the same line-balance logic used to diagnose slow cells, reviewed in the line balancing guide.
Time should be reserved in the commissioning plan for changeover trials. A cell that only proves one format has not proven the product range. Run at least the main SKU and a second, smaller or differently shaped format through a full changeover, timing the setup, checking the recipe recall and confirming the change parts are accessible and stored. Seasonal or future SKUs that cannot be tested yet should be listed as a follow-up check once that product arrives.
Operator involvement during commissioning matters more than buyers often allow. If the supplier’s technician runs every trial, the plant team watches rather than learns. Have the operators perform the setup, changeover, jam clearing and routine check under supervision, and record which tasks they can complete unaided before handover. That hands-on practice surfaces unclear instructions and missing documentation while the supplier is still on site. The preventive routines those operators will maintain afterward are in the preventive maintenance guide.
Acceptance milestones and commercial terms
The acceptance process should line up with the commercial milestones in the purchase order. A common structure ties part of the payment to the FAT passing and the balance to SAT acceptance on site, which keeps the supplier accountable through handover rather than releasing all terms at shipment. The order should state what each milestone requires: which test cases, what defect level, which documents, and who signs off. Vague language such as “machine works to satisfaction” leaves the acceptance standard open to argument later; written criteria remove that ambiguity.
Warranty and response terms should be confirmed at this stage too. Note the warranty period, what it covers and excludes, the response commitment for a stopped line, and the parts-continuity window after the model is built. Where the plant runs multiple shifts, ask whether support availability matches those shifts, and how spare parts are stocked locally or shipped. These terms are easiest to settle before the order, when the buyer still holds the stronger bargaining position, rather than after install when the machine is already in production.
For buyers ordering from a supplier in another region, the acceptance record also supports customs, compliance and later service claims. Keep the FAT and SAT reports, serial numbers, configuration and spare-parts list together, so a service visit or a warranty question can reference the exact installed machine. The regional support and parts continuity considerations are reviewed in the spare parts and commissioning support note and the supplier continuity guide.
One practical note for the acceptance file: record the actual measured rate and defect rate during the SAT, not the quoted peak. The measured baseline is what later comparisons use, whether you are judging a later drift, planning an expansion, or reviewing whether the machine met the original case. Note the product mix, shift length and any conditions that affected the trial, so the baseline can be interpreted fairly months later. This measured record is also the starting point for any line-balancing or capacity review, and it keeps the commissioning phase useful long after the supplier has left the floor. Treat the acceptance file as a working baseline, not a signed-off form to archive, and revisit it whenever a new SKU, shift or product type changes how the cell runs.
References and background sources
The commissioning practice in this note follows standard end-of-line engineering and our floor audits. Standards and market context draw on public sources: the ISO 13849-1 machinery safety standard on control-system safety performance, the PMMI market research overview on packaging machinery and automation, and the interpack trade fair overview on equipment trends. Rate and defect figures are planning references only; your acceptance basis should follow the written specification and the standards applicable to your market.