TL;DR. Interpack 2025 (Düsseldorf, May 2025) showcased the packaging industry’s shift toward automation, sustainability and digital twins. For buyers in 2026, the show’s takeaways are clear: expect 20–30% longer lead times, demand EtherNet/IP and OPC-UA connectivity from day one, and specify film-reduction features on every new machine. This article breaks down what the show’s exhibitors actually launched, and what it means for your next RFQ.
By Ryan Huang, Sales Application Engineer. Ryan attended Interpack 2025 and has tracked the exhibitor announcements for end-of-line buyers.
1. What Interpack 2025 showed
PMMI’s Interpack 2025 recap noted that sustainability — film gauge reduction, mono-material recyclability, and energy-efficient drives — was the dominant theme across end-of-line exhibits. The second theme was connectivity: nearly every exhibitor showed OPC-UA or EtherNet/IP-enabled machines, with digital twin commissioning becoming a standard sales pitch.
Statista’s industrial robotics data corroborates the trend: robotic case packing and palletizing were the most-visited exhibits at the show, with cobot cells drawing the largest crowds from small and mid-sized plant operators.
2. Three takeaways for buyers
| Theme | What exhibitors showed | What to spec in 2026 |
|---|---|---|
| Film reduction | 200%+ pre-stretch carriages, 17 μm film capability | Adjustable pre-stretch 100–300%, not fixed |
| Connectivity | OPC-UA / EtherNet/IP on every machine | Require it in the RFQ; reject proprietary protocols |
| Energy efficiency | Servo drives, standby mode, regenerative braking | Ask for kWh/year rating; budget 15% premium |
3. What this means for your buying decision
- Spec adjustable pre-stretch (100–300%) on every new stretch wrapper — fixed-ratio carriages are now obsolete.
- Require OPC-UA or EtherNet/IP in the RFQ. If a supplier cannot name the protocol, walk away.
- Ask for kWh/year on the energy rating. A 15% premium on an efficient machine pays back in 3–5 years on electricity.
- Plan lead times: Interpack exhibitors reported 24–30 week lead times on robotic cells. Issue RFQ 6 months before installation.
- Ask for a digital twin or simulation before acceptance. It catches layout mistakes before steel is cut.