TL;DR. PMMI’s 2025 industry outlook flags end-of-line automation — case packing, palletizing and stretch wrapping — as the largest investment priority for CPG plants in 2026–2027, with 68% of surveyed manufacturers planning new projects. Lead times have stretched to 18–30 weeks, and used equipment prices have firmed. This article breaks down what the data means for buyers specifying equipment now.
By Ryan Huang, Sales Application Engineer. Ryan has helped 40+ plants spec end-of-line equipment and track PMMI’s annual capital spending surveys.
1. What PMMI reported
PMMI’s 2025 industrial outlook surveyed 400+ CPG manufacturers and found that end-of-line equipment — case packing, palletizing and stretch wrapping — is the number-one capital spending category for 2026–2027. The key drivers are persistent labour shortages at distribution centres, and the need to handle e-commerce’s growing SKU count on the same line that used to run one SKU.
Statista’s industrial robotics dataset corroborates: unit shipments of robotic arms in packaging grew ~12% in 2024, with palletizing as the single largest application.
2. Why end-of-line, not upstream
Upstream filling and forming lines were already automated 10–20 years ago. The remaining labour-intensive gap is at the end: operators still erect, pack, seal, stretch-wrap and palletize by hand in a huge share of plants. Each of those stations is a candidate for a $50k–$200k automation project with an 18–30 month payback. That maths is why the spending surge is concentrated at the end of the line.
3. Lead times are real
| Equipment | 2022 lead time | 2026 lead time |
|---|---|---|
| Semi-automatic stretch wrapper | 4–6 weeks | 8–12 weeks |
| Automatic case sealer | 6–8 weeks | 12–16 weeks |
| Robotic palletizer cell | 16–20 weeks | 24–30 weeks |
| Case erector + packer line | 12–16 weeks | 20–26 weeks |
4. What this means for your buying decision
- Issue RFQ 6 months before you need the machine installed, not 3.
- Prioritise local parts stock over headline price — a 2-week parts delay on a 24/7 line costs more than the price difference.
- Spec for 30% volume growth, not today’s volume. You cannot re-order in 8 weeks.
- Consider used 2021–2023 cells in good condition: lead time is days, not months.
- Budget 10–15% contingency on top of the machine quote for conveyor and guarding.